Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.
Alexander Road North (until mid May 2025)
Reinstatement works are underway at the north end of Alexander Road following drainage works earlier this year. The PSP at the north end of Alexander and under the Thomas Road bridge will also be completed by mid May.

Larsen Road pedestrian bridge
The Larsen Road pedestrian bridge is open.
Temporary lighting will be used on the bridge until permanent lighting is installed. Bridge finishing works will continue, and intermittent pedestrian and cyclist traffic management will be in place.
For the Larsen Road level crossing removal fact sheet, please click here.
George Street Carpark works (until mid May 2025)
Work has begun to construct several carparks on the western verge of George Street. Works will include the removal of soil, compacting, asphalting and kerbing. There will be no road closures and minimal disruption to traffic during these works.

Byford Station works
Works are ongoing to construct the new Byford Station and associated facilities. Works include structural steel installation, building fit-out, service installation, roofing for the platforms and walkways, as well as bus canopy, cladding, and fascia installation.