Works Yanchep Rail Extension

Alkimos and Butler

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. For all out-of-hours works, please contact the site supervisor directly on 0437 845 471.


Butler Station to Romeo Road

Lane closures (ongoing)

The southbound lane of Duerden Street will be closed until late-March to enable the safe construction of limestone walls along the rail corridor and provide a safe working distance between excavations and live traffic. Property access will be maintained at all times; however parking along the eastern verge will be unavailable.

The purpose of this closure is to enable the safe construction of limestone walls along the rail corridor and provide a safe working distance between excavations and live traffic. Property access will be maintained at all times however parking along the eastern verge will be unavailable.


Noise walls (ongoing)

Until early-2024, there will be an increase in noise during works on Chesham Rise, between Cheadle and Jeresh lanes to build noise walls. 

Sections of Chesham Rise will close intermittently with traffic management in place.


Earth works (ongoing) 

Until early-2024, there will be works on the verges of Chesham Rise, Charlbury Drive, Amble Grove, Werner Street, Duerden Street, Jeresh Lane and Vike Lane to reinstate footpaths, install traffic barriers and place topsoil and mulch. 

Intermittent lane closures will be required to complete works and water carts will be used to manage dust.


Rail

Until early-2024 rail works will commence in the corridor from 6am.

Until early-2024, from 7pm – 3am there will be occasional rail works to install ballast, overhead line equipment, grind and compact rails, and test trains. These works will continue during standard working hours.

From Friday 8 until Monday 11 March 2024, there will be continuous works 24/7 to undertake track works along the rail corridor between Hester Avenue and Yanchep Station. There will be interruptions to passenger services from Butler Station during these works.

For information about service disruptions to the Joondalup Line please visit the Transperth website.


Romeo Road to Shorehaven Estate

Earth works (ongoing) 

Until early-2024, there will be works on the verges of Maroon Avenue and Buchanan Avenue to reinstate footpaths, install traffic barriers and place topsoil and mulch. 

Intermittent lane closures will be required to complete works and water carts will be used to manage dust.

There will be a potential increase in noise during out-of-hours works at the Alkimos Station site, north of Romeo Road, for station construction and rail installation.

Until early-2024, occasional concrete pours from 4am to build retaining walls.


Noise walls (ongoing) 

Until late-March, there will be intermittent road closures and an increase in noise during works to install noise walls on both sides of the rail corridor at Maroon Avenue and Buchanan Avenue, between Bluewater Drive and Bainbridge Avenue.


Rail

Until early-2024 rail works will commence in the corridor from 6am.

Until early-2024, from 7pm – 3am there will be occasional rail works to install ballast, overhead line equipment, grind and compact rails, and test trains.

These works will continue during standard working hours.


Bainbridge Avenue and Buchanan Avenue Alkimos (until February 2024)

Road closures (ongoing)

We are proposing to extend the temporary road closure of Bainbridge Avenue between Buchanan Avenue and Decatur Street, and Buchanan Avenue between Cushing Road and Bainbridge Avenue for a period of four months until late May 2024. 
 
The purpose of the temporary road closure is to enable site access to safely excavate the corridor to rail level, construct retaining walls, and install noise walls. This closure will enable critical finishing works for the Yanchep Rail Extension. 
 
Access across the rail corridor is maintained by the new connections built at Maroon Avenue, Alkimos Drive Bridge and Pardo Street, which are now open to traffic.

230927 - Alkimos Drive connection-TMP-03

A public comment period is now open and plans detailing the area affected by the closure may be inspected at the City of Wanneroo Civic Centre, 23 Dundebar Road, Wanneroo.

Submissions may be lodged in writing to the Chief Executive Officer by:

Email: traffic@wanneroo.wa.gov.au, or

Post: City of Wanneroo, Locked Bag 1, Wanneroo WA 6946

Submissions close on Thursday 14 March 2024 at 5pm.

 

Yanchep

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. For all out-of-hours works, please contact the site supervisor directly on 0437 845 471. 


Jindowie Estate to Yanchep Beach Road

Noise walls (until early-2024)

There will be intermittent road closures and an increase in noise during the installation of noise walls on both sides of the rail corridor along Bulburin Parade, Cocoparra Parkway and Abercrombie Avenue.

Traffic management will be in place.


Earth works (ongoing)

Until early-2024, there will be works on the verges of Bulburin Parade, Cocoparra Parkway, Abercrombie Avenue and Yanchep Beach Road to reinstate footpaths, install traffic barriers and place topsoil and mulch.

Intermittent lane closures will be required to complete works and water carts will be used to manage dust.


Pre-cast yard (ongoing)

Until early-2024, a concrete pre-cast yard will be established on the corner of Blackwood Meander and Bulburin Parade.

There will be intermittent concrete pours including occasional 4am starts due to weather conditions.

The site will be accessed by Morwell Street.


Rail

Until early-2024 rail works will commence in the corridor from 6am.

Until early-2024, from 7pm – 3am there will be occasional rail works to install ballast, overhead line equipment, grind and compact rails, and test trains.

These works will continue during standard working hours.

From Friday 8 until Monday 11 March 2024, there will be continuous works 24/7 to undertake track works along the rail corridor between Hester Avenue and Yanchep Station. There will be interruptions to passenger services from Butler Station during these works.

For information about service disruptions to the Joondalup Line please visit the Transperth website.


Yanchep Beach Road to Toreopango Avenue

Wall construction (ongoing)

Until early 2024, there will be works between Intempo Place and Capilano Avenue Yanchep for wall construction, which will include earth works, piling and concrete pours. 
Concrete pours may take place out of hours due to weather conditions. 
Construction vehicles will access the area via Spinnaker Boulevard and Castlemead Drive. 

Earth works (ongoing)

Until early-2024, there will be works on the verges of Capilano Avenue to place topsoil and mulch.

Intermittent lane closures will be required to complete works and water carts will be used to manage dust.


Yanchep Beach Road (ongoing)

Yanchep Beach Road has been realigned with lanes open to traffic in both directions, with a speed reduction of 40km/hr in place.

Future short-term closures, lane closures and intermittent out-of-hours works may be required to safely build the surrounding rail infrastructure, with traffic management in place.


Booderee Road (ongoing)

The intersection of Booderee Road and Yanchep Beach Road will be closed until late-May 2024.  

The purpose of the road closure is to enable asphalt, verge works, pavement marking, and various finishing works.


Rail

Until early-2024 rail works will commence in the corridor from 6am.

Until early-2024, from 7pm – 3am there will be occasional rail works to install ballast, overhead line equipment, grind and compact rails, and test trains.

These works will continue during standard working hours.

From Friday 8 until Monday 11 March 2024, there will be continuous works 24/7 to undertake track works along the rail corridor between Hester Avenue and Yanchep Station. There will be interruptions to passenger services from Butler Station during these works.

For information about service disruptions to the Joondalup Line please visit the Transperth website.

News

Eglinton

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. For all out-of-hours works, please contact the site supervisor directly on 0437 845 471.


Shorehaven Estate to Allara Estate

Earth works (until early-2024)

There will be a possible increase in noise, dust and vibration during verge works on Marmion Avenue between Revolution Avenue and south of Pipidinny Road.

Traffic will be reduced to a single lane in both directions.

Shared path detours will be in place east of Marmion Avenue and a section of the shared path west of Marmion Avenue and south of Pipidinny Road will be closed. 


Pipidinny Road (ongoing)

Pipidinny Road is open with traffic management in place as works continue in the area.

Short-term lane closures are required to safely build Eglinton Station.


Rail

Until early-2024 rail works will commence in the corridor from 6am.

Until early-2024, from 7pm – 3am there will be occasional rail works to install ballast, overhead line equipment, grind and compact rails, and test trains. 

These works will continue during standard working hours. From Friday 8 until Monday 11 March 2024, there will be continuous works 24/7 to undertake track works along the rail corridor between Hester Avenue and Yanchep Station. There will be interruptions to passenger services from Butler Station during these works.

For information about service disruptions to the Joondalup Line please visit the Transperth website.

 

Phone

(08) 9326 3666

Gnarla Biddi

METRONET acknowledges the Whadjuk and Gnarla Kaarla Boodja people as the Traditional Custodians of the land and waters on which the program of projects is located.

Aboriginal and Torres Strait Islander people are advised that this site may contain names, images or voices of people who are deceased.

Copyright (c) 2024 METRONET
Back To Top