Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call the METRONET Info Line 24/7 on 9326 3666.
Out-of-hours works will be conducted at Alkimos, Eglinton and Yanchep stations, precincts, within the rail corridor and outside in surrounding areas, and at stockpiles from Monday to Sunday, 7pm – 7am until September 2024. Works include various rail completion and testing works, finishing works including landscaping, placement of topsoil and mulch, road works involving asphalting, kerbing, sealing and completing road, footpaths, access ways and car parks, preparation of shared paths, minor civils works, installation of signage, barriers and fencing, and earthmoving. There may be an increase in noise and vibration, heavy plant and equipment, and light vehicle traffic in areas including the use of residential streets. All works will follow approved noise and out-of-hours management plans and regular water carts will be operating to manage dust. There may be intermittent lane and road closures to facilitate works.
Butler Station to Romeo Road
Butler Station
Out-of-hours works will be carried out at the Butler Station until September 2024. Works will include the construction of emergency services stairs into the rail corridor, installation of noise walls and completion works within the rail corridor and areas surrounding the station.
Until mid-2024, the Butler Station bus bay will be temporarily closed to facilitate cranes lifting precast footing, stairs and handrails into the corridor for access works. Work vehicles, trucks and machinery will be active in the area and follow approved traffic management plans. Concrete pours will be needed for foundations. There may be an increase in noise, dust and vibration with compactions works required.
Noise wall works continue to be constructed and commuters could expect a reduction in parking areas close to station entrance to provide a safe working distance between works and live traffic. Commuters should access the overspill parking bays located on the eastern side of Doncaster Grange.
Intermittent Lane closures (ongoing)
Intermittent lane closures will be in place to conduct completion works across the project including footpath reinstatement, utility works and minor earth works including emergency access into the rail corridor and the construction of limestone walls. Lane closures are likely to include Santorini Promenade, Duerden Street, Werner Street, Chesham Rise, Charlbury Drive, Halesworth Parade and Vike Lane to provide a safe working distance between works and live traffic.
Noise walls (ongoing)
Until mid-2024, works will continue along Werner Street and Duerden Street to construct a limestone noise wall. There will be intermittent road closures with traffic management in place and detours where required. Work vehicles, trucks and machinery will be active in the area and follow approved traffic management plans. There may be an increase in noise and dust during the installation of walls.
Ongoing finishing works will continue on Chesham Rise Property access will be maintained at all times however parking along the eastern verge may continue to be unavailable.
Earth works and finishing works (ongoing)
Until mid2024, there will be works on the verges of Chesham Rise, Charlbury Drive, Amble Grove, Werner Street, Duerden Street, Jeresh Lane, Vike Lane and Halesworth Parade, to reinstate footpaths, install traffic barriers, signage and place topsoil, mulch and landscaping where required. Intermittent lane closures or road closures will be required to complete works. Water carts and street sweepers will be used to manage dust.
Road Closure
Until 10 July 2024, completion works along Chesham Rise will require a temporary road closure between Dixie Way and Jerash Lane as the team works southward to reinstate the footpath and complete finishing works in the area. The road will be closed and detours in place. Traffic management will be on site.
Rail
There will be continuous rail works within the rail corridor and surrounding areas from Butler Station to Yanchep Station. There may be interruptions to passenger services from Butler Station.
Until mid-2024, out-of-hours rail commissioning and testing works will be conducted. Works may include track, signalling, communications, installations of rail infrastructure and overhead line equipment. Both compaction and test trains will be operating. The majority of works will be conducted during standard working hours, however out-of-hours works including night works are required.
Romeo Road to Shorehaven Estate
Completion Works
Until mid-2024, there will be out-of-hours completion works Monday to Sunday from 7pm to 7am. Works include various rail completion and testing works, finishing works including landscaping, placement of topsoil and mulch, road works involving asphalting, kerbing, sealing and completing roads, footpaths, access ways, car parks, minor civils works, installation of signage, barriers and fencing, and earthmoving. There may be an increase in noise and vibration, heavy plant and equipment, and light vehicle traffic in areas including the use of residential streets.
Intermittent lane closures will be required to complete works and water carts and street sweepers will be used to manage dust.
Noise walls (ongoing)
Until September 2024, there may be intermittent road or lane closures and an increase in noise during works to install or conduct completion works to noise walls on both sides of the rail corridor at Maroon Avenue and Buchanan Avenue, between Bluewater Drive and Bainbridge Avenue.
Rail
There will be continuous rail works within the rail corridor and surrounding areas from Butler Station to Yanchep Station. There may be interruptions to passenger services from Butler Station.
Until mid-2024, out-of-hours rail commissioning and testing works will be conducted. Works may include track, signalling, communications, installations of rail infrastructure and overhead line equipment. Both compaction and test trains will be operating. The majority of works will be conducted during standard working hours; however, of-hours works including night works are required.
Bainbridge Avenue and Buchanan Avenue Alkimos (until May 2024)
Road closures (ongoing)
Until mid-2024, there could be ongoing road closures from Bainbridge Avenue between Buchanan Avenue and Decatur Street, and Buchanan Avenue between Cushing Road and Bainbridge Avenue to enable site access to complete noise walls, paint walls, install barriers, conduct landscaping and conduct completion works.
Alkimos Vista
Noise walls (until early-2024)
Until August 2024, works will be underway to construct a limestone noise wall along Masterpiece Boulevard. The southbound lane along Masterpiece Boulevard will be closed with intermittent closures from the roundabout at Picasso Promenade north to Sketch Street.
Work vehicles, trucks and machinery will enter the area from Marmion Avenue on to Picasso Promenade. There may be an increase in noise, dust and vibration during the installation of walls. Traffic management will be in place and detours where required.